CONSTRUCTION SITE MANAGEMENT and CONTROLLING



What Is Construction Site Management?


  • Managing the design and construction of a stated project to achieve an architectural and construction program at the lowest beneficial cost to owner within reasonable profit framework for the participants.
  • The basic function of managing the design and construction process as currently constituted is the integration of various independent factions through planning organizing and controlling
  • Management function is an agency of the owner may be performed by owner ,delegated to the contractor ,the architect or an independent party ,or some combination thereof
  • Construction management is more than just procedure it is a process that generates a facility at the lowest reasonable cost
  • The success of the construction management will be achieved through planning, organizing and controlling thus the construction manager must comprehend contemporary techniques of management
  • An ability to organize the efforts of all participant to maintain control of the contract interface, to expedite progress and to quickly reach rational decisions required
  • The construction manager is an agent of the owner , an association with legal and operational consequences that affect construction management practice .legally ,an agent agrees to subordinate authority to serve the interest of client
  • Group of management activities over and above normal architectural and engineering services related to a construction program ,carried out during design and construction phases ,that contributes to the control of time and cost in a new facility
  • Construction management is more the bringing together of many proven management techniques than it is the development of something entirely new
  • In general terms it is the application of available construction knowledge and management technique applied by a firm acting as the owner agent to project plan /design/build/occupy/process


Why It Exists?

Inflation:
The need to combat inflation was a major contributing factor in the rise if construction management. Before construction management was considered separate field ,time and cost control was shared by the design professional and the contractor    .the contractor kept a schedule and designer kept a record of cost .this system prove beneficial until about fifteen years ago when inflation become a major concern .construction management has been able to counteract the effect of progressively rising construction cost by reducing the time required between the identification of need for a facility and occupancy. Streamlining procedure both in terms of reaching decision and of processing information, fast tracking or early bidding of critical construction contract using performance specification  while details are being designed and restricting the extent and time for owner reviews are used to compress the conceive / design / period/ build

Better project control:
One of the reason for the rise of construction management is better project control and often, and owner must rely on knowledgeable and experienced organization for specialized constructed based decision. However the ability to make this decision is meaningless unless the decision maker can also implement properly. Consequently, the leaders of such an organization must adeptly manage the staff that issues decision and processes the documents that directs the work. Centralized authority should improve decision making by placing responsibility at the level where all factors that affect the total project can be considered and evaluated according to their relative contribution to the successful completion of project. Thus, better control systems from the organization a construction manager provides.

Use of sophisticated management techniques:
Better project control is closely related to sophisticated management and construction related techniques. Standard management related techniques include decision trees, risk adjusted utility analysis, and game theory; construction related techniques involve accelerated construction, value engineering, critical path schedules, life cost analysis, and range estimating.
These tools are the methods used to effectively implement construction management, and they can be considered an end as well, since society will gain from more efficient buildings constructed at lower costs and in less time.

Construction knowledge during design:
Construction management also hopes to forestall potential problems by introducing practical construction knowledge in the early phases of design. Traditionally, design professionals are artists with little knowledge of actual construction practices.They often include details in the contract documents that are not logical to construct or do not achieve the desired aesthetic result. Since the contract documents specifically define constructed methods and imply assembly techniques, the owner would be paying for the product that was not only more expensive but less suitable than needed. The application of construction understanding during the early phases of project design helps to improve design efficiency.

Control of costs:
Improved control of construction costs during design is another factor. Traditionally designers would generate bid documents without detailed, accurate cost information. If the bids received were too high, either the owner increased the budget, often using his or her contingency to do so, or the project had to be redesigned.
Recently, pressure to adhere to an owner’s budget has required that design professionals include statements of probable construction costs at various phases of their basic services.
However the design professional does not guarantee construction costs and maintain, in reserve the ability to alter the project scope so that it will fall within 10% of probable construction costs, if the bids are excessive. If inflation were 15% an 8 month delay to redesign a project that is 10% over the owner’s budget may require a 20% reduction in scope to keep the project feasible.

Team Effort instead of competition:
Traditionally the construction industry is disorganized, since different segments complete their work isolation from each other. When design professionals prepare contract documents before they are presented to the contractor for pricing, they do not get the benefit of that team member’s input. Since ambiguities and conflicts do occur, the general conditions of the contract documents usually provide a “grandfather clause” that requires contractors and sub contractors to immediately point out problems and discrepancies to design professional for interpretation and clarification. Occasionally there are penalties; more often they are not. In any case owner loses.
Construction management aims to coordinate the actions of the two into a team effort and thereby reduce conflicts and ambiguities that cannot be readily resolved.


Objectives:
Any site or project will have objectives in these spheres;


  • Time completion is required within a certain time.
  • Costs expected project costs versus benefits will enable rewards or profits to be made.
  • Quality completion is required within criteria which measure standards achieved against standards required or specified.
  • Performance project performance is required to satisfy the time, cost and quality parameters


These are no necessarily presented in order of importance for every project but do reflect, nevertheless the natural order:

If you do not have the time, you will not
If you do not have the money, you cannot
If you do not know what you want, you will never get it.

Take time first. Probably you have heard of plans and planning you may even prepared or taken part in some. So what is the mystery element or elements which distinguish successful plan works. The only true answer is that the successful plan works. The likely explanation is that the plan is recognized as being one of the main factors for success the others being both derived from and included in the plan and covering, perhaps the allocation and effective use of resources, cost control and the means for achieving the agreed standards.

The cost next- everybody knows what money is and what can be done with it. In project considerations, though, the focus is on particular aspects of the use of money and you will deliberately plan and to get something for a certain price you negotiate each step of the way. The cost aspect is thus broken down into three project areas:


  • Estimating
  • Accounting
  • Control

Preparing an estimate obviously takes both time and money. The results depend upon these factors as well as the skill and experience of the estimations and the brief to which they work
Project accounting is essentially the book keeping exercise. It records expenditures into predetermined account codes and classifies them into categories such as capital funds, indirect/ direct overheads, materials, field labour, plant, etc
Project cost control on the other hand is the dynamic aspect of the project cost arena,\. Essentially it combines the estimate of time and money together with the accounting record for the expressed purpose of control, i.e. asking action.


Factors:

Cost:
Project cost must be achieved comprehensively and include the cost of designing, delivering, constructing, and furnishing the project.
In an inexpensive project the lead time between the preliminary design and the final working drawings is normally several weeks or months. Consequently the potential cost savings to the owner, of employing either accelerated delivery or sophisticated coordination techniques, is relatively small. The contractor can usually complete such projects with relative ease within the time span required to prepare the necessary contract documents.
      If the project is more costly and, accordingly, more time is required to adequately document the design, then the techniques of construction management begin to make sense. For a more expensive project, the cost of construction management services will be offset by the overall savings gained from finishing the project sooner. Hence, services that coordinate, expedite, and improve the quality of a project should be seriously considered.

Complexity:
If a project is relatively simple, with a high degree of duplication, the project need not be accelerated, even if it is large or expensive. Because there is substantial duplication and standardization of components, contract documents can be completed and coordinated in relatively short time and then bid as an entire package. This would give the owner the benefit of receiving firm prices for all of the work prior to any construction.
As project complexity increases, better planned and coordinated documents are necessary if the bids are to accurately reflect the work required and if the construction is to have few problems. Such coordination will necessitate increased design time, and consequently, project expediting techniques become feasible. However complexity does not preclude the use of construction management to organize the construction of different facilities within the project
         In short, increased complexity lends itself to the adoption of project expediting processes. If a project is complex, increased coordination of design, detail, and construction will be required. Such coordination extends the project time; construction management will reduce it. Consequently, construction management should be considered to improve the project schedule, delivery, and cost.

Size:
When a project is large, it can be divided into separate and distinct sub projects. For example, a new college campus will often contain specialized academic buildings, all of which are required in a basic educational program.
By adopting construction management procedures, critical buildings are identified and scheduled for expedited completion so that the entire campus is completed at the earliest date.
If separate sub projects are identified and work within each is divided into separate contracts, there is greater possibility that coordination problems will occur at the interface. The construction manager must coordinate each separate sub project and tenant work within each segment of the overall project construction. Consequently if facility is large and complex, the construction manager must attend and help coordinate each contract interface. He must not establish intervening contracts that would interfere with each contractor’s performance. Certainly all sub contracts are related to each other ; each is necessary to complete the work. However once a sub contract begins, there should be no intervening sub contracts that would prevents its completion.  Nevertheless, a separate contract should never be allowed to intervene between the fabrication and installation of any single contract without giving each contractor the right to bid and perform those contracts that affect the work and profit.

Time:
In every contract, time is of the essence. In construction, control of time is critical. If the duration of a project is relatively long, there is a greater opportunity to apply construction   management methods to gain efficiency and reduce time.
Every project participant has the incentive to reduce time. When the contractor’s price is fixed, reducing duration will increase his profit. The same incentive is true for the design professional who works for a lump sum or a percentage of the construction costs.
         When the design and construction of a project are expected to be lengthy, the overall cost and project duration can be reduced, provided the project team maintains an expedited project schedule. Unless the owner’s chain of command and delegation of responsibility are clear, the project decision processes will take considerable time, increase the cost, and extend the project’s completion.
The construction manager should evaluate, during the preliminary design process, the dedication of the owner and the owner’s staff to the principle of reaching a fast, but not hasty, decision before any phase of the project goes into construction

Experience:
Some owners can more readily utilize construction management services than others, especially if they need the construction of facilities as part of their normal business.
This experience often eliminates many of the problems and decisions that may occur during the design sequence. The same is true for government and publicly regulated agencies that provides a standard service in each of their geographically dispersed facilities.
The experience of the owner’s staff is also a factor that contributes to expediting project processes. When the owner realizes the importance of making decisions based on practical knowledge and understands that delays are costly, the project will advance.
However one important note of caution: construction management organizations are often hired by communities to provide consultant management services for a specific large scale venture. The construction management must establish communication channels with existing public departments that maintain base data information. Often the construction management organizations structure will not correspond with the bureaucratic organization of the public department. Yet there must be communication among all levels of both organizations.
This will facilitate communication between the two interdependent bodies and bypass the long line of communication involved in upward referral.

Different Approaches:

When construction management is enlisted to benefit the delivery of a project, critical decisions must be made regarding the packaging, phasing, and bidding of the construction work. Publicly funded projects require open bidding, with no contractor pre qualification. Many private owners will also want the benefit of open, competitive bidding, but often with the pre qualification of the contractor. Two construction management approaches to project assembly have resulted from this bid requirement.


DESIGN ASSEMBLED APPROACH:
The design assembled approach divides the work according to design and documentation phases, with no pre established contractor/construction manager. The design professional divides the work into packages based on construction documentation. As previously discussed, general work will begin after the general design is complete. Hence, each package covers a different phase of the work. A separate general contractor will take complete responsibility for each package and will procure bids from subcontractors needed to help complete this phase. One possible drawback of this delivery method is that the owner cannot look to a sole contracting entity to take overall responsibility for the project’s construction effort. The design professional will, have to coordinate the bid packages and evaluate each contractors responsibilities at the contract interface.
        In the design assembled approach, the design professional, in effect becomes the construction manager, and the owner will look to that individual to carry out this coordination. The design professional must not only make certain that all work is covered in documents, but must also designate in which phase the installation is required.
            In any case, issues such as these must be resolved by the professional and all decisions accurately reflected in the documents of the design assembled approach. The engineering and cost benefit evaluations for each alternative must be made concurrently with the concurrently with the decision on the overall approach to project delivery. These evaluations techniques will be discussed later.

SEGREGATED CONTRACT APPROACH:
The segregated contract approach divides the work according to established construction subcontract divisions. The segregated contract manager usually has a contracting background. This individual is selected on the basis of merit, not necessarily on the lowest price. During the planning stage he/she can advise without acting in conflict of interest, even though he/she may eventually participate in a subsequent construction phase, if no bid for a portion of the work is received or if the lowest bid is too high.
With this type of assembly, the segregated contract manager will oversee the work of those who would normally be subcontractors and material suppliers in conventional delivery. However, because of the requirements of public bidding, these usual subcontractors will compete with others within their specialty trade for a separate contract direct with the owner. Each segregated contractor will perform specialty work to the requirements of the design professional’s documents and in accordance with the schedule established by the segregated contract manager.
There are advantages to the segregated contract approach. This industry based method of assembling the work does allow accelerated delivery. The owner receives the direct bid from each segregated contractor without a general contractor’s handling
fee and markup. In this type of delivery the owner usually pays the segregated contract manager a fixes fee for basic services and reimburses the contract manager for variable costs, which include jobsite expense. This means that all parameters of costs are out in the open, except for unforeseen document clarifications, changes, or extraordinary expenses, all of which are covered in the owner’s contingency fund. Because of such objectivity and its reputation for minimizing costs, this approach is often applied.



Stages Of Activities:

The stages of activities representing any time of work is given below

Clear site: necessary before any survey work can start.

Survey and layout: cannot start before the site is cleared; otherwise, many of the survey stakes would be lost in the clearing operation.

Rough grade: cannot start until the area has been laid out. This activity ties up the whole site with earth moving equipment.

Drill well: cannot start until the rough grading operation’s completed

Drive and pour piles: after layout, this is the first step in the plant and warehouse

Excavate: follows piling. This is fine grading to finish grade

Spread footing: can be placed after the excavation is done.

Form and pour grade beams: are poured on top of spread footings.

Backfill and compact: is done after the grade beams are finished.

Form and pour slabs: can be done after he under slab preparations are complete.

Erect structural steel: follows the completion of foundations.

Masonry partitions: start as soon as building is closed in

Ceiling works: is supported as soon as building is closed in.

Exterior doors: can be hung after the building is closed in but must be installed prior to the dry wall.

Hand interior doors: can follow dry wall installation

Ceramic tile: can follow dry wall

Floor tile: should be held off until room painting is complete

Insulate heating and ventilating ducts: cannot be done until ductwork is in place

Fabricate piping system: can be done after the building is closed in.

Erect roof: naturally must follow the erection of the structure. Since it uses the same crane rising, it follows closely.

Exterior masonry: follows the roof erection

Paint exterior: starts after the roofing is on and doors are installed.

Controlling:

The control phase of a project is continually measuring and controlling
all variances throughout all phases of a project life cycle..



An accurate snapshot of the actual project (where it is) and with the
planned status (where it is supposed to be) must be made at regular
intervals, as this is the only way to control a project.



The aim of project control, in a nutshell, is to compare the actual
progress and performance against the project plan. The project manager
therefore has to analyze any variances, review possible alternatives, and
take the appropriate corrective action. Undoubtedly, project managers
need to control their projects on a regular basis; without this control
being in place, an ever-increasing level of unnecessary detail will appear.

The prime role during this phase is to
(a) Identify all symptoms or factors that would jeopardize the
project and
(b) Outline the process for bringing the project back on track.

Controlling can be done using a basic, three-step process.


  • Determine project status and if objectives are being met.
  • Compare the status against project planning.
  • Assess the cause of problems and implement corrective actions.

The Cost Control System

During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools serve the dual purpose of recording the financial transactions that occur as well as giving managers an indication of the progress and problems associated with a project. The problems of project control are aptly summed up in an old definition of a project as "any collection of vaguely related activities that are ninety percent complete, over budget and late." The task of project control systems is to give a fair indication of the existence and the extent of such problems
The limited objective of project control deserves emphasis. Project control procedures are primarily intended to identify deviations from the project plan rather than to suggest possible areas for cost savings. This characteristic reflects the advanced stage at which project control becomes important. The time at which major cost savings can be achieved is during planning and design for the project. During the actual construction, changes are likely to delay the project and lead to inordinate cost increases. As a result, the focus of project control is on fulfilling the original design plans or indicating deviations from these plans, rather than on searching for significant improvements and cost savings. It is only when a rescue operation is required that major changes will normally occur in the construction plan.
Finally, the issues associated with integration of information will require some discussion. Project management activities and functional concerns are intimately linked, yet the techniques used in many instances do not facilitate comprehensive or integrated consideration of project activities. For example, schedule information and cost accounts are usually kept separately. As a result, project managers themselves must synthesize a comprehensive view from the different reports on the project plus their own field observations. In particular, managers are often forced to infer the cost impacts of schedule changes, rather than being provided with aids for this process. Communication or integration of various types of information can serve a number of useful purposes, although it does require special attention in the establishment of project control procedures.
The Project Budget
For cost control on a project, the construction plan and the associated cash flow estimates can provide the baseline reference for subsequent project monitoring and control. For schedules, progress on individual activities and the achievement of milestone completions can be compared with the project schedule to monitor the progress of activities. Contract and job specifications provide the criteria by which to assess and assure the required quality of construction. The final or detailed cost estimate provides a baseline for the assessment of financial performance during the project. To the extent that costs are within the detailed cost estimate, then the project is thought to be under financial control. Overruns in particular cost categories signal the possibility of problems and give an indication of exactly what problems are being encountered. Expense oriented construction planning and control focuses upon the categories included in the final cost estimation. This focus is particular relevant for projects with few activities and considerable repetition such as grading and paving roadways.
For control and monitoring purposes, the original detailed cost estimate is typically converted to a project budget, and the project budget is used subsequently as a guide for management. Specific items in the detailed cost estimate become job cost elements. Expenses incurred during the course of a project are recorded in specific job cost accounts to be compared with the original cost estimates in each category. Thus, individual job cost accounts generally represent the basic unit for cost control. Alternatively, job cost accounts may be disaggregated or divided into work elements which are related both to particular scheduled activities and to particular cost accounts. Work element divisions will be described in Section 12.8.
In addition to cost amounts, information on material quantities and labor inputs within each job account is also typically retained in the project budget. With this information, actual materials usage and labor employed can be compared to the expected requirements. As a result, cost overruns or savings on particular items can be identified as due to changes in unit prices, labor productivity or in the amount of material consumed.
Controlling the Site Schedule
Construction typically involves a deadline for work completion, so contractual agreements will force attention to schedules. More generally, delays in construction represent additional costs due to late facility occupancy or other factors. Just as costs incurred are compared to budgeted costs, actual activity durations may be compared to expected durations. In this process, forecasting the time to complete particular activities may be required. There are several ways to update the schedule. The most frequently used methods are percent completed, remaining duration, duration completed, estimated completion date, and actual start and actual finish dates. The goal is to provide enough information to compare accurately the present project status to the planned target. Any delay in project implementation places the project at risk of possibly being overtaken by technological change. If this is the case, it is vital that project plans are flexible enough to allow for the insertion of newer technologies when they are released.
Some of the schedule issues that need to be controlled are
•Erroneous activity sequencing (incorrect WBS)
•Project tasks being incorrect because the quantities of resources are unavailable.
•Changing requirements (which always require additional rework
and time)
•Incorrect or unrealistic activity duration estimates

 

Control of Project Cash Flows

These components include costs incurred (as described above), billings and receipts for billings to owners (for contractors), payable amounts to suppliers and contractors, financing plan cash flows (for bonds or other financial instruments), etc

The job status reports illustrated in this and the previous sections provide a primary tool for project cost control. Different reports with varying amounts of detail and item reports would be prepared for different individuals involved in a project. Reports to upper management would be summaries, reports to particular staff individuals would emphasize their responsibilities (Eg. purchasing, payroll, etc.), and detailed reports would be provided to the individual project managers. Coupled with scheduling reports described in Chapter 10, these reports provide a snapshot view of how a project is doing. Of course, these schedule and cost reports would have to be tempered by the actual accomplishments and problems occurring in the field. For example, if work already completed is of sub-standard quality, these reports would not reveal such a problem. Even though the reports indicated a project on time and on budget, the possibility of re-work or inadequate facility performance due to quality problems would quickly reverse that rosy situation.

Schedule and Budget Updates

Scheduling and project planning is an activity that continues throughout the lifetime of a project. As changes or discrepancies between the plan and the realization occur, the project schedule and cost estimates should be modified and new schedules devised. Too often, the schedule is devised once by a planner in the central office, and then revisions or modifications are done incompletely or only sporadically. The result is the lack of effective project monitoring and the possibility of eventual chaos on the project site.
On "fast track" projects, initial construction activities are begun even before the facility design is finalized. In this case, special attention must be placed on the coordinated scheduling of design and construction activities. Even in projects for which the design is finalized before construction begins, change orders representing changes in the "final" design are often issued to incorporate changes desired by the owner.
Periodic updating of future activity durations and budgets is especially important to avoid excessive optimism in projects experiencing problems. If one type of activity experiences delays on a project, then related activities are also likely to be delayed unless managerial changes are made. Construction projects normally involve numerous activities which are closely related due to the use of similar materials, equipment, workers or site characteristics. Expected cost changes should also be propagated thoughout a project plan. In essence, duration and cost estimates for future activities should be revised in light of the actual experience on the job. Without this updating, project schedules slip more and more as time progresses. To perform this type of updating, project managers need access to original estimates and estimating assumptions.
Unfortunately, most project cost control and scheduling systems do not provide many aids for such updating. What is required is a means of identifying discrepancies, diagnosing the cause, forecasting the effect, and propagating this effect to all related activities. While these steps can be undertaken manually, computers aids to support interactive updating or even automatic updating would be helpful.
Beyond the direct updating of activity durations and cost estimates, project managers should have mechanisms available for evaluating any type of schedule change. Updating activity duration estimations, changing scheduled start times, modifying the estimates of resources required for each activity, and even changing the project network logic (by inserting new activities or other changes) should all be easily accomplished. In effect, scheduling aids should be directly available to project managers
Controlling Project Resources

The responsibility of managing the correct quantity of resources on a
project is demanding. Project managers must ensure that sufficient
resources are used on all project activities that were planned earlier
during the project-planning phase. In many situations, there are either
too little or too many staff members performing these tasks, and it
becomes the responsibility of the project manager to level these
resources out and to maintain the right amount of resources on the task.
It doesn't make any financial sense to keep additional resources on the
project if they won't be used again.

So, these members will likely have to
be released. If the resources have specialist skills that are considered
crucial to the client, then the necessary arrangements must be made to
retain those resources.

If, however, if too few resources working on an important task that has to be completed within a certain date, then there are a few options available
•Add additional staff members from other tasks to the important
task, hoping to reduce the duration.
•Hire additional resources just for the task duration.



resource leveling

Controlling Project Costs:

The project manager must capture, track, and control all project-related
costs that are incurred against planned project cost items. Whether it is
project timesheets, hardware, or travel expenses, it is essential that all
costs be reflected against the project. This provides a realistic measure of
what the project cost the company at the end of the day. Additionally, it
also helps measure how well the project was planned.
It is necessary that these costs be captured on the project system that
the project manager is using. In the event where unforeseen costs arise,
it is the project manager's responsibility to immediately compare the cost
item (invoice) against the planned project cost WBS task. If there is a
difference, it implies a loss on the specific WBS work package, not
necessarily on the total project. If the tendency is similar on many of the
WBS tasks, then it is probable that the project will be heading for a loss,
indicating bad planning and estimation. There is nothing that the project
manager is able to do. To aid the project managers in cost control, the
following items need to be verified:

  •The budget allocations are accurate and correct.
  •The original project estimate and budget are correct.
  •The original prices used to develop the estimate still apply and
   are firm.
  •Technical difficulties will affect the cost of the project.

However, when costs are incurred against the project and it is found that
an actual cost item is slightly higher than the planned WBS cost, , for the project must remain profitable to the company, no more additional cost overruns can be tolerated. The costs must now be controlled even more than ever. Remember, depending on the contract value, the overall project will not immediately reflect this loss; initially only single WBS items reflect this loss.

Organizing for Quality and Safety
A variety of different organizations are possible for quality and safety control during construction. One common model is to have a group responsible for quality assurance and another group primarily responsible for safety within an organization. In large organizations, departments dedicated to quality assurance and to safety might assign specific individuals to assume responsibility for these functions on particular projects. For smaller projects, the project manager or an assistant might assume these and other responsibilities. In either case, insuring safe and quality construction is a concern of the project manager in overall charge of the project in addition to the concerns of personnel, cost, time and other management issues.
Inspectors and quality assurance personnel will be involved in a project to represent a variety of different organizations. Each of the parties directly concerned with the project may have their own quality and safety inspectors, including the owner, the engineer/architect, and the various constructor firms. These inspectors may be contractors from specialized quality assurance organizations. In addition to on-site inspections, samples of materials will commonly be tested by specialized laboratories to insure compliance. Inspectors to insure compliance with regulatory requirements will also be involved. Common examples are inspectors for the local government's building department, for environmental agencies, and for occupational health and safety agencies.
The US Occupational Safety and Health Administration (OSHA) routinely conducts site visits of work places in conjunction with approved state inspection agencies. OSHA inspectors are required by law to issue citations for all standard violations observed. Safety standards prescribe a variety of mechanical safeguards and procedures; for example, ladder safety is covered by over 140 regulations. In cases of extreme non-compliance with standards, OSHA inspectors can stop work on a project. However, only a small fraction of construction sites are visited by OSHA inspectors and most construction site accidents are not caused by violations of existing standards. As a result, safety is largely the responsibility of the managers on site rather than that of public inspectors.
While the multitude of participants involved in the construction process require the services of inspectors, it cannot be emphasized too strongly that inspectors are only a formal check on quality control. Quality control should be a primary objective for all the members of a project team. Managers should take responsibility for maintaining and improving quality control. Employee participation in quality control should be sought and rewarded, including the introduction of new ideas. Most important of all, quality improvement can serve as a catalyst for improved productivity. By suggesting new work methods, by avoiding rework, and by avoiding long term problems, good quality control can pay for itself. Owners should promote good quality control and seek out contractors who maintain such standards.
In addition to the various organizational bodies involved in quality control, issues of quality control arise in virtually all the functional areas of construction activities. For example, insuring accurate and useful information is an important part of maintaining quality performance. Other aspects of quality control include document control (including changes during the construction process), procurement, field inspection and testing, and final checkout of the facility.
Work and Material Specifications
Specifications of work quality are an important feature of facility designs. Specifications of required quality and components represent part of the necessary documentation to describe a facility. Typically, this documentation includes any special provisions of the facility design as well as references to generally accepted specifications to be used during construction.
General specifications of work quality are available in numerous fields and are issued in publications of organizations such as the American Society for Testing and Materials (ASTM), the American National Standards Institute (ANSI), or the Construction Specifications Institute (CSI). Distinct specifications are formalized for particular types of construction activities, such as welding standards issued by the American Welding Society, or for particular facility types, such as the Standard Specifications for Highway Bridges issued by the American Association of State Highway and Transportation Officials.
These general specifications must be modified to reflect local conditions, policies, available materials, local regulations and other special circumstances. Construction specifications normally consist of a series of instructions or prohibitions for specific operations. For example, the following passage illustrates a typical specification, in this case for excavation for structures:
Conform to elevations and dimensions shown on plan within a tolerance of plus or minus 0.10 foot, and extending a sufficient distance from footings and foundations to permit placing and removal of concrete formwork, installation of services, other construction, and for inspection. In excavating for footings and foundations, take care not to disturb bottom of excavation. Excavate by hand to final grade just before concrete reinforcement is placed. Trim bottoms to required lines and grades to leave solid base to receive concrete.
This set of specifications requires judgment in application since some items are not precisely specified. For example, excavation must extend a "sufficient" distance to permit inspection and other activities. Obviously, the term "sufficient" in this case may be subject to varying interpretations. In contrast, a specification that tolerances are within plus or minus a tenth of a foot is subject to direct measurement. However, specific requirements of the facility or characteristics of the site may make the standard tolerance of a tenth of a foot inappropriate. Writing specifications typically requires a trade-off between assuming reasonable behavior on the part of all the parties concerned in interpreting words such as "sufficient" versus the effort and possible inaccuracy in pre-specifying all operations.
In recent years, performance specifications have been developed for many construction operations. Rather than specifying the required construction process, these specifications refer to the required performance or quality of the finished facility. The exact method by which this performance is obtained is left to the construction contractor. For example, traditional specifications for asphalt pavement specified the composition of the asphalt material, the asphalt temperature during paving, and compacting procedures. In contrast, a performance specification for asphalt would detail the desired performance of the pavement with respect to impermeability, strength, etc. How the desired performance level was attained would be up to the paving contractor. In some cases, the payment for asphalt paving might increase with better quality of asphalt beyond some minimum level of performance.

Total Quality Control

Quality control in construction typically involves insuring compliance with minimum standards of material and workmanship in order to insure the performance of the facility according to the design. These minimum standards are contained in the specifications described in the previous section. For the purpose of insuring compliance, random samples and statistical methods are commonly used as the basis for accepting or rejecting work completed and batches of materials. Rejection of a batch is based on non-conformance or violation of the relevant design specifications. Procedures for this quality control practice are described in the following sections.
An implicit assumption in these traditional quality control practices is the notion of an acceptable quality level which is a allowable fraction of defective items. Materials obtained from suppliers or work performed by an organization is inspected and passed as acceptable if the estimated defective percentage is within the acceptable quality level. Problems with materials or goods are corrected after delivery of the product.
In contrast to this traditional approach of quality control is the goal of total quality control. In this system, no defective items are allowed anywhere in the construction process. While the zero defects goal can never be permanently obtained, it provides a goal so that an organization is never satisfied with its quality control program even if defects are reduced by substantial amounts year after year. This concept and approach to quality control was first developed in manufacturing firms in Japan and Europe, but has since spread to many construction companies. The best known formal certification for quality improvement is the International Organization for Standardization's ISO 9000 standard. ISO 9000 emphasizes good documentation, quality goals and a series of cycles of planning, implementation and review.
Total quality control is a commitment to quality expressed in all parts of an organization and typically involves many elements. Design reviews to insure safe and effective construction procedures are a major element. Other elements include extensive training for personnel, shifting the responsibility for detecting defects from quality control inspectors to workers, and continually maintaining equipment.
Worker involvement in improved quality control is often formalized in quality circles in which groups of workers meet regularly to make suggestions for quality improvement. Material suppliers are also required to insure zero defects in delivered goods. Initally, all materials from a supplier are inspected and batches of goods with any defective items are returned. Suppliers with good records can be certified and not subject to complete inspection subsequently.
The traditional microeconomic view of quality control is that there is an "optimum" proportion of defective items. Trying to achieve greater quality than this optimum would substantially increase costs of inspection and reduce worker productivity. However, many companies have found that commitment to total quality control has substantial economic benefits that had been unappreciated in traditional approaches. Expenses associated with inventory, rework, scrap and warranties were reduced. Worker enthusiasm and commitment improved. Customers often appreciated higher quality work and would pay a premium for good quality. As a result, improved quality control became a competitive advantage. Of course, total quality control is difficult to apply, particular in construction. The unique nature of each facility, the variability in the workforce, the multitude of subcontractors and the cost of making necessary investments in education and procedures make programs of total quality control in construction difficult. Nevertheless, a commitment to improved quality even without endorsing the goal of zero defects can pay real dividends to organizations.
CONTROLLING RISK:

Risk control is the process of continually assessing the condition of the
project and developing options to permit alternative solutions
Project managers should take care to identify consequences that are
likely to occur and any indicators of the start of the problem.
The following are some suggestions for risk control:
•Continually update the risk management plan.
•Implement risk avoidance actions.
•Implement risk contingency actions.
•Report on each risk issue.
•Monitor and analyze the effectiveness.
 


Safety
Various measures are available to improve jobsite safety in construction. Several of the most important occur before construction is undertaken. These include design, choice of technology and education. By altering facility designs, particular structures can be safer or more hazardous to construct. For example, parapets can be designed to appropriate heights for construction worker safety, rather than the minimum height required by building codes.
Choice of technology can also be critical in determining the safety of a jobsite. Safeguards built into machinery can notify operators of problems or prevent injuries. For example, simple switches can prevent equipment from being operating when protective shields are not in place. With the availability of on-board electronics (including computer chips) and sensors, the possibilities for sophisticated machine controllers and monitors has greatly expanded for construction equipment and tools. Materials and work process choices also influence the safety of construction. For example, substitution of alternative materials for asbestos can reduce or eliminate the prospects of long term illnesses such as asbestiosis.
Educating workers and managers in proper procedures and hazards can have a direct impact on jobsite safety. The realization of the large costs involved in construction injuries and illnesses provides a considerable motivation for awareness and education. Regular safety inspections and safety meetings have become standard practices on most job sites.
Pre-qualification of contractors and sub-contractors with regard to safety is another important avenue for safety improvement. If contractors are only invited to bid or enter negotiations if they have an acceptable record of safety (as well as quality performance), then a direct incentive is provided to insure adequate safety on the part of contractors.
During the construction process itself, the most important safety related measures are to insure vigilance and cooperation on the part of managers, inspectors and workers. Vigilance involves considering the risks of different working practices. In also involves maintaining temporary physical safeguards such as barricades, braces, guy lines, railings, toe boards and the like.
Sets of standard practices are also important, such as
  • Requiring hard hats on site.
  • Requiring eye protection on site.
  • Requiring hearing protection near loud equipment.
  • Insuring safety shoes for workers.
  • Providing first-aid supplies and trained personnel on site
While eliminating accidents and work related illnesses is a worthwhile goal, it will never be attained. Construction has a number of characteristics making it inherently hazardous. Large forces are involved in many operations. The jobsite is continually changing as construction proceeds. Workers do not have fixed worksites and must move around a structure under construction. The tenure of a worker on a site is short, so the worker's familiarity and the employer-employee relationship are less settled than in manufacturing settings. Despite these peculiarities and as a result of exactly these special problems, improving worksite safety is a very important project management concern
Conclusion:

Construction management is not really a new concept; only recently has it become a dominant force in construction. It exists as a new profession in response to economic pressures and the lack of clear project leadership within the construction industry proper.
               Nonetheless, construction management has succeeded where others failed. Not only, it has incorporated modern management techniques and advanced construction controls, but more importantly, it works within the framework of today’s construction industry by retaining the specialized activities of design professional and contractor under its control. Since construction management techniques can readily adopted in almost every construction venture, construction management provides a reasonable way to deliver a project that meets an owner individual preferences and specific project requirements. 























Waterproofing in Construction Industry

     In building construction, a structure needs waterproofing since concrete itself will not be watertight on its own (but note concrete is easily waterproofed with additives). The conventional system of waterproofing involves 'membranes'. This relies on the application of one or more layers of membrane (available in various materials: e.g., bitumen, silicate, PVC, EPDM etc.) that act as a barrier between the water and the building structure, preventing the passage of water. However, the membrane system relies on exacting application, presenting difficulties. Problems with application or adherence to the substrate can lead to leakage. In the UK these membranes are rarely allowed below ground below the water table.
Over the past two decades, the construction industry has had technological advances in waterproofing materials, including integral waterproofing systems as well as more advanced membrane materials.
Integral systems work within the matrix of a concrete structure, giving the concrete itself a waterproof quality. There are two main types of integral waterproofing systems: the hydrophilic and the hydrophobic systems. A hydrophilic system typically uses a crystallization technology that replaces the water in the concrete with insoluble crystals. Various brands available in the market claim similar properties, but not all can react with a wide range of cement hydration by-products, and thus require caution. Hydrophobic systems use fatty acids to block pores within the concrete, preventing water passage.
New membrane materials seek to overcome shortcomings in older methods like PVC and HDPE. Generally, new technology in waterproof membranes relies on polymer based materials that are extremely adhesive to create a seamless barrier around the outside of a structure.
Damp proofing in Residential Buildings
Water Proofing for Roofs


Case Study in brief
We have narrated in brief about the system of waterproofing, its wide classification and also the latest waterproofing methods in the present trend. As for as our assignment is concern, we took a case study of an industrial building (220KV Power station- Dubai) where we can see the conventional method of waterproofing works being carried out for substructure and roof slab. 
Classification of waterproofing            Waterproofing shall be classified under the following categories,
Classification based on structureClassification based on technology
Classification based on Structure

Based on structure, it is classified as
Sub- structural water proofing (e.g.: below ground level)Super-structural water proofing (e.g.: Roof)

Sub- structural water proofing: There are quite lot many ways that are followed on structural basement waterproofing works and some of the common and unique techniques of waterproofing using specific branded compounds are as follows.
HOW TO WATERPROOF BASEMENT




Compound Used: Ames'® Super Primer, Vapor Barrier
Brand name        : AMES1. Surface preparationAlways run a test patch first in an inconspicuous area, to ensure that proper adhesion and drying occurs and the product works to your satisfaction. Careful and complete preparation will ensure the best results, and contribute to the life of the coating. The wall surface must be clean, dry, and free of loose material. Loose or peeling paint should be removed with a wire brush, and rough wood surfaces sanded. Do not apply Vapor-Barrier™ over wet, loose, or crumbling concrete. Repair the concrete, and allow curing. Mildew may be removed with a power washer. Fill all joints or cracks wider than 1/8 inch with a Blue Max trowel-grade coating & filler. Follow seam taping instructions. Mask all sensitive areas before starting.2. Prime the surface with Ames' Super PrimerIt is important to seam tape all joints and cracks to avoid future cracking and leaking. Apply around flashings, windows and cracks in the walls. Refer to Ames' Seam Tape label for application instructions. Do not use fiberglass or asphalt impregnated seam tape.Super Primer penetrates into the concrete. It is pearlescent blue as it is being applied, drying to a clear, slightly tacky surface. This process begins the waterproofing. Apply at a rate of 1 gallon per 100 square feet (estimated).
                Super Primer is drying almost as fast as it can be sprayed onto the surface.3. Apply Ames' Vapor-BarrierApply at least 2 coats of Vapor-Barrier, our waterborne, liquid rubber, elastomeric coating. At this point the surface should be impenetrable to water. All minor cracks and crevices will be sealed. Apply at a rate of 2 gallons per 100 square feet. Recommended milage is 20 to 35 mils (or the thickness of a dime or quarter). Drying time will be approximately 30 to 60 minutes on warm days with sun contact.     This application can be used on: foundations, bearing walls, cisterns or water storage tanks, and other concrete surfaces. Vapor-Barrier is potable water compliant.Clean-up, Storage, Disposal and Thinning Clean up tools and small spills with water. Store unused product in its original can, tightly sealed at 45 to 85 degree F. Dispose of this product in accordance with state, federal, and local requirements. May thin up to 10% with water.                                       Weather & Drying Guidelines Ames' Coatings are best applied between 40 to 90 degrees F. on warm dry surfaces. Apply when the streets are dry, the sun is in the sky, and no inclement weather is forecast. Dries in 1-2 hours, depending on thickness of application and weather; and cures in 24 hours. Low temperatures, high humidity, and evening or morning dew will require increased drying/curing time.Estimated Coverage: Super Primer: apply at a rate of 1 gallon per 100 square feet (estimated). Vapor Barrier: Apply at a rate of 2 gallons per 100 square feet.HOW TO SEAL OR WATERPROOF THE LEAKING BASEMENT?1. Surface Preparation Read all label instructions before beginning. Always run a test patch first in an inconspicuous area, to ensure that proper adhesion and drying occurs and the product works to your satisfaction.Careful and complete preparation will ensure the best results and contribute to the life of the coating. The wall surface must be clean, dry, and free of moss and loose material. Loose or peeling paint should be removed with a wire brush and rough wood surfaces sanded. Concrete surfaces may be prepared by using a disc grinder and carborundum disc or sand blasting. Do not apply over wet, loose or crumbling concrete. Repair the concrete and allow to cure completely. Mildew may be removed with a power washing. New concrete should be allowed to cure for at least 30 days prior to application of this product. Fill all joints or cracks wider than 1/8 inch with Blue Max™ trowel grade coating and filler. Follow all seam-taping instructions. Mask all sensitive areas before starting.Be sure the concrete is dry before beginning. Drying the basement wall out completely before proceeding will be necessary. Use of a propane space heater as needed may be necessary to complete this task. Construction space heaters may be rented or purchased. Allow proper ventilation. Primer penetration and curing will be dependent on a dry surface.
2. Prime the Surface and Seamtape Joints and CracksPrime the surface with Ames' Blue Max Liquid Rubber. It is important to seam tape all joints and cracks to avoid future cracking and leaking. Our Peel & Stick Seam Tape is a self-adhesive, high-strength, contouring seam tape that is easy to apply. For the best adhesion prime all surfaces with Ames'® Blue Max before applying seam tape. Refer to Ames' Seam Tape application guide for application instructions. Do not use fiberglass or asphalt impregnated seam tape as a substitute. Use only Ames' Tapes. Once the seam tape has been placed over the primer it will be next to impossible to remove. The seamtape is pliable, so it is easy to shape with your fingers, even to corners. Warning! Do not uses asphalt sealers. They do not really water proof. Asphalt will simply float over damp surfaces. When the petroleum evaporates the owner is eventually left with nothing but prehistoric animal pigment.3. Application Ames' Block & Wall™ Liquid Rubber or Blue Max may be applied by brush, roller or sprayer. Shake or stir Block & Wall Liquid Rubber prior to use. Apply a minimum of one gallon per 100 sq. ft. per coat. Two coats minimum, three to four is superior. The application must be applied in a continuous, unbroken seal of a minimum dry thickness of no less than 30 mils (the thickness of a dime) over the entire surface.Good: Prime the concrete surface with one or two coats of Blue Max and then apply one or more coats of Ames' Block and Wall Liquid Rubber coating at a rate of one or two gallons/per/100 square feet. One or two coats of Ames' Block & Wall Liquid Rubber or Blue Max will cover and waterproof in most cases. Use all the product estimated for the job in order to achieve the proper millage.
Better: First prime with Blue Max over the concrete. Then apply two to three coats or three gallons per 100 square feet of Block & Wall Liquid Rubber or Blue Max. Use the entire product to achieve the proper millage.
Best: This type of heavy-duty application is normally used when applied on a below grade surface where a severe waterproofing situation might exist. This procedure is generally used on new commercial building applications where long-term heavy-duty applications might be required. The very best product application is five gallons per 100 sq. ft. or three to five coat application systems necessary for long term waterproofing. In this application fabric can be applied over most smooth surfaces and is generally embedded in the second layer of the liquid rubber. The fabric becomes saturated and is sandwiched in the coating and allowed to dry for additional reinforcement. It applies like fiberglass. The fabric is polyester and shapes like fiberglass and will never rot or deteriorate. This application is nearly impervious to water penetration when properly done and expected to last up to twenty plus years. It can also be applied to concrete or wood surfaces such as concrete roofs where bare concrete has begun to deteriorate. Concrete roofs are often in need of special attention especially in the tropics when rains are heavy and concrete is decomposing. Otherwise this application is usually not necessary unless the surface is in danger of deteriorating since these coatings are extremely elastic. On above grade applications apply two to three coats of Blue Max followed by two coats (2 gallons per 100 square feet) of Ames' Block & Wall waterproofing paint or Ames' Paint and Prime Paint and Prime is tintable.
Weather & Drying Guidelines Ames' Coatings are best applied between 40 to 90 degrees F. on warm dry surfaces. Apply when the streets are dry, the sun is in the sky, and no inclement weather is forecast. Dries in 1-2 hours, depending on thickness of application and weather; and cures in 24 hours. Low temperatures, high humidity, and evening or morning dew will require increased drying/curing time.
BASEMENT WATERPROOFING USING PIPELINE TECHNIQUESWe were called out to provide a solution for a water problem in a basement. The basement was not properly tanked during the construction phase. None tanking can result in major waterproofing problems in the future - Our client experienced between 10mm-30mm of water ponding on the entire floor of the basement. A permanent water pump was installed to pump out the water.The builders had penetrated an unforeseen but very real underground 'river' during construction. Water penetrated from both the floor and the construction joints between the walls of the basement.
                                  Diagram of basement showing level of water
                                  Diagram showing construction joint in a basementHow to properly tank a basement retaining wall?Step One Excavate around the basement down to foundation level. This is best done during construction phase when no excavation is needed.
Step twoApply generous amounts of Bitumen Primer by means of block brush or roller to all the areas that will receive the torch on membrane
Step threeHeat fuses the torch on membrane to the primed areas.
Torching is quite tricky and should only really be done by persons who have experience in this.
Step fourConnect the pieces of flow pipe and wrap in bedim cloth
Flow pipe is a pipe with holes in it.
The pipe allows water to pass into it and flow away to a storm water outlet.
Bedim cloth is a geo textile that act likes a filter to stop sand and other objects entering the pipe
Tip: It is important to get the levels of the flow pipe falling correctly. It would be best to consult a drainage expert on this. Some council regulations demand that plans be approved for drainage systems
Step fiveSurround the flow pipe with 19mm builder stone.
The stone acts as the first filter
Step sixBack fill with clean sand
How to waterproof concrete roofs?Waterproofing concrete with roof coatings is an important task on concrete structures for roof repair and preservation. Many roofs throughout the world are constructed using poured concrete. These structures are usually made with reinforced steel. They are inexpensive but require a great deal of maintenance to keep them from leaking since they shift, move, and dissolve easily. The problem with concrete is that it IS concrete. Concrete is made up from several ingredients including calcium carbonate and sand. Calcium Carbonate is a plentiful substance that comes from the dead skeletons of sea life. These plentiful substances dissolve quite easily in very wet environments unless they are protected.
The Ames specializes in the making of specialty rubber and plastic coatings that extend the life of concrete. These products stretch with the concrete and form a waterproof membrane. Unfortunately, untreated concrete cracks and dissolves in many geographic areas where there is a great deal of rain. In the wintertime, water leaks into the untreated cracks and freezes and expands substantially damaging your concrete building.
Before beginning any project, read all instruction labels. Always run a test patch first in an inconspicuous area, to ensure that proper adhesion and drying occurs and the product works to your satisfaction
Usually a concrete structure is composed of four walls of poured concrete and a poured concrete roof. Walls and parapet walls, both outside and inside, over the roof need to be water proofed. Both outside walls and inside walls should always be considered to be a part of your waterproofing tasks. The building should be thought of as a total building envelope. If you have stucco on the outside of the building, use Ames “Super Primer” and then “Paint & Prime®” to waterproof the stucco or concrete surface.
PREPARE THE SURFACEHow to fix flat roofs or concrete roofs with “roof coatings” is really a simple process even for the “do it yourselfer”. The first thing you should do is to power wash the entire surface area of the roof, which will remove most of the loose material. Use caution, so as not to damage any interior areas due to roof leakage that are inside the building. In certain situations, a shot-blaster may be needed to roughen the surface. In addition, it might be a good idea to fill any large cracks and crevices with mortar.
PRIME THE SURFACEAfter preparing the surface you will need to prime the roof with Ames Pure Acrylic Plastic primer, “Super Primer”. Super Primer will dry rapidly and will flow into the cracks and crevices of the concrete rooftop. It will bond to the concrete with remarkable adhesion. Super Primer has an affinity for concrete and it actually glues together and strengthens old concrete surfaces. Read all instruction labels before beginning. Always run a test patch first in an inconspicuous area, to ensure that proper adhesion and drying occurs and the product works to your satisfaction.
SEAM TAPENext, seam tape all remaining cracks larger than one-eighth of an inch. Seam tape with “Ames Peel & Stick” Seam tape. This tape comes in 2 inch, 4 inch, and 6 inch widths by 50-foot rolls. This rubber tape contours easily to the surface and will stick with the most remarkable adhesion to the primed surface. The seam tape will be difficult to remove from here on out.
TOPCOAT OVER THE SURFACEApply at least two gallons per 100 sq. ft. of “Super Elasto-Barrier” or similar Ame's product. Finally, apply two to three gallons per 100 sq. ft. of Ames Maximum Stretch elastomeric acrylic plastic coating. Super Primer, Seam Tape, Super Elasto Barrier, and “Maximum-Stretch” are an unbeatable combination for concrete roofs.


DRAINAGE
Proper drainage is also an important factor on concrete roofs. With this application, you will be substantially strengthening the concrete with the pure acrylic plastic Super Primer. Followed by the rubber “Super Elasto-Barrier”. Be sure to apply seam tape where the vertical and horizontal concrete joints meet at the parapet roof and wall joints. The parapet wall and cap also need to be water proofed. This combination of coatings, as well as the outside of the parapet wall, should be waterproofed with Ames “Paint & Prime”.
ROOF DECKS
If the surface is a roof deck application and you wish to walk on your roof, then you can apply Ames “Safe-T- Deck” non-skid durable plastic paint as your final coat. This product comes in a variety of colors. Lighter colors are best for areas in high heat. Dark colors in the northern hemispheres.
The drawing below describes a basic product application. 
CONCRETE ROOF
1. Always run a test patch first to ensure that proper adhesion and drying occurs and the product works to your satisfaction. The whole concrete roof is cleaned and power-washed, then flood coated with Ames' Super Primer, pure acrylic primer.
2. Repair large holes with concrete patch. Seam tape large cracks with Ames' Peel & Stick adhesive seam tape.
3. For best results, topcoat the concrete roof surface with Ames' Super Elasto-Barrier and Maximum-stretch.
CONCRETE WALLS
1. Always run a test patch first to ensure that proper adhesion and drying occurs and the product works to your satisfaction. The whole concrete wall is cleaned and power-washed.
2. Repair large holes with concrete patch. Seam tape large cracks with Ames' Peel & Stick adhesive seam tape.
3. For best results, topcoat the concrete wall surface with Ames' Super Primer and Ames' Paint & Prime All-In-One premium acrylic paint.
Seal and Waterproof an Existing Chimney
 Always run a test patch first in an inconspicuous area, to ensure that proper adhesion and drying <![if !vml]><![endif]>occurs and the product works to your satisfaction.
<![if !vml]><![endif]>
Clean and Prepare the Surface
Clean the surface, and scrape or remove loose debris before starting your project. Be sure surfaces are clean and dry before seam taping or the coating application.
 Seam Taping
<![if !vml]><![endif]>The purpose of seam taping is to provide reinforcement over areas prone to splitting, such as seams, cracks or joints, and create a “bridge” that ties the surfaces together so water cannot seep through. Peel & Stick Seam Tape is self-adhesive. Measure out the length of Seam Tape needed and press into place.
 Apply Super Elasto-Barrier To The Chimney
Apply Ames' Super Elasto-Barrier, a waterborne liquid dual-rubber Coating as a primer over the seam tape and the rest of the chimney surface. Super Elasto-Barrier is up to 1000% Elastic. It may <![if !vml]><![endif]>be brushed rolled or sprayed.
Topcoat with Ames Coatings
A topcoat of Ames' Maximum-Stretch or other Ames coating may be applied to the chimney.
Weather & Drying Guidelines
Ames Coatings are best applied between 40 to 90 degrees F. on warm dry surfaces. Apply when the streets are dry, the sun is in the sky, and no inclement weather is forecast. Dries in 1-2 hours, depending on thickness of application and weather, and cures in 24 hours.
Low temperatures, high humidity, and evening and morning dew will require increased drying/curing time.
Estimated Coverage
Standard product coverage on a smooth surface is 100 sq. ft. per gallon (est. 10ml). More than one coat recommended. More coats equal longer life.

Waterproofing for Metal Roofs

Ames industrial metal roof coatings are your first choice in metal roof waterproofing and metal roof repair. Ames premium metal roof coatings are formulated especially for commercial and residential metal roofs, recreational Vehicles (RV's), mobile homes, steel roofs and aluminum roofs. Ames coatings are water base, non-toxic, VOC-free and have low odor. They are easy to apply and are water clean-up.
<![if !supportLists]>v <![endif]>Storm Damage
<![if !supportLists]>v <![endif]>Leaking Metal Roofs
<![if !supportLists]>v <![endif]>Rusty Metal
<![if !supportLists]>v <![endif]>Oxidized Aluminum

1. Surface Preparation
The roof must be dry. Remove loose dirt, flaking rust, and debris from the roof surface. Refasten any screws or nails that may have worked loose. Be sure surfaces are clean and dry before the coating application. Caulk all cracks greater than 1/8” wide with Blue Max™ trowel-grade coating and filler.
2. Seam Tape & Prime the Roof Surface
Prime with 1-3 coats of Super Elasto-Barrier™, Maximum-Stretch™ or Iron Coat™ until the roof surface is smooth and sealed. Let cure so that it's dry to the touch. Surfaces with joints, cracks, flashings, vents, parapet wall flashings or where two unlike surfaces come together, require Ames’® Peel & Stick Seam Tape (PS250, PS450, PS650) to provide some additional strength and reinforcement.

1. Peel off the backing
2. Line tape up with seam
3. Press firmly into place.
3. Pour it out and Paint it on
Apply coating as needed for a durable, hard shell, thermo-reflective surface.
Clean up, Storage, Disposal and Thinning
Clean up tools and small spills with water. Store unused product in its original can, tightly sealed at 45 to 85 degree F. Dispose of this product in accordance with state and federal and local requirements. Thin with water up to 10%.
Weather and Drying Guidelines
Best results when applied between 40 to 90 degrees F on warm dry surfaces. Apply when the streets are dry, the sun is in the sky and no inclement weather is forecast. Dries in 1-2 hours, depending on thickness of application and weather; cures in 24 hours. Low temperatures, high humidity and evening and morning dew will require increased drying/curing time.
Estimated Coverage
Standard product coverage on a smooth surface is 100 sq. ft. per gallon per coat (est. 10ml). More than one coat recommended. More coats equal longer life.
A Suggested Metal Roof Application

Apply Roof Fabric
For use on:
<![if !supportLists]>v  <![endif]>Smooth tar roofs
<![if !supportLists]>v  <![endif]>Roof decks
Advantages:
<![if !supportLists]>v  <![endif]>Lasts longer
<![if !supportLists]>v  <![endif]>Added strength
<![if !supportLists]>v  <![endif]>Keeps the roof from splitting
<![if !supportLists]>v  <![endif]>Reduces movement
Ames'® Polyester Contouring Roof Fabric adds substantial strength to the coating of roof surfaces. It reinforces the coating to resist ripping and tearing. Roof Fabric increases penetration resistance. It may be cut to different widths for specialized jobs. Roof Fabric is especially useful for roof decks and gutter areas and may be used over plywood, concrete, metal and many other surfaces.

Do-It-Yourself in three easy steps
Roof Fabric is normally set with Super Elasto-Barrier , but in special cases may be set with Maximum-Stretch, Snow Seal®, or Iron Coat. Surface preparation is everything. Prepare the roof by removing dirt, moss and other debris. Power wash and let dry thoroughly. Prime the roof smooth and apply seam tape and Super Elasto-Barrier to all joints and seams.
Step one: Starting at one end pour out a liberal amount of coating onto the surface. Use a push broom or roller to spread the coating out in a path slightly wider than the roof fabric being used. Roll the fabric into the wet coating until the coating comes up through the fabric and totally saturates it. This is best done by laying the roll of fabric down and pushing it forward into the wet coating with the push broom or roller while the excess coating comes up through the fabric. Avoid folds and wrinkles. Use a liberal amount of coating. The fabric will absorb almost two gallons per 100 square feet.
Step two: With the roller or push broom, pull the excess coating off to the side in preparation for laying the next row of fabric. Use the lap line on the fabric roll as a guide. One may butt or overlap the fabric. If you choose to overlap the fabric, overlap its entire length by three to four inches. Overlap may leave a seam. Repeat this process until the entire surface is completely covered with fabric. Allow to dry completely 24 to 48 hours.
Step three: To complete the roof fabric application process, apply an additional coat over the surface to completely seal and fill all remaining pinhole openings in the fabric. The goal is to have all pinholes filled and no less than 30 miles of thickness (a dime). The coating is best applied by pouring out and spreading. Topcoat with Ames' Maximum-Stretch, Safe-T-Deck or Snow Seal according to label specifications. Allow proper drying between coats.

Classification based on Technology
Nano Technology in Water Proofing:
Abstract:
Water intrusion in building materials has been a problem for the last 1000 years. Regrettably, this problem was never fully addressed due to a lack of understanding on a Nano scale. Fortunately, new developments in science and technology have incorporated the use of Nano technology to produce eco-friendly, Organo-Silicon products that can render most cementitious materials hydrophobic for cycles of 20 to 30 years or more at a very economical cost.
Introduction:
Building materials are known to have water seepage and water leaks due to inherent porosity and micro cracks. Water repellency can be achieved through treatments, which are expected to render cementitious materials impervious to water. Over the last 50 years, a significant amount of technology has been developed utilizing various methodologies. One of the most common methods utilized a blend of basic polymeric chemistry and other materials to create products that are resistant to water intrusion.

Water Repellents:
One of the primary objectives of water repellents is to maintain and preserve aesthetics, by protecting cementitious substrates from water related issues such as:
                       
<![if !supportLists]>v <![endif]>Paint peel-off
<![if !supportLists]>v <![endif]>Paint blisters
<![if !supportLists]>v <![endif]>Fungus
<![if !supportLists]>v <![endif]>Mold & Mildew
<![if !supportLists]>v <![endif]>Efflorescence
In addition to aesthetic preservation, water repellents address more serious structural issues such loss of structural strength of concrete building materials due to ASR (alkali silica reaction), acid rain, and sulphate attack. Water repellents can also prevent chloride penetration, which often results in the corrosion of the reinforced steel bars.
Water related problems
– Most cementitious building materials are very porous and have surface hydroxyl groups. These hydroxyl groups attract water because of the hydrophilic nature and similarity with the structure of water.  Therefore, most cementitious building materials easily absorb water into the pores when water is present. The size of the water molecule is 0.18 nm (nanometer = 10-9 meter, i.e. .00018 microns).  The pore size in most cementitious building
materials range from 5 to 200 nm.  Most pollutants such as acids, chlorides, and sulphates range between 1 to 2 nm. Even the most dense concrete and stones and have pore sizes much larger than water which enable both water and other damaging chemicals to easily penetrate the pore structure of these materials.
As the world has started to pay more attention to aesthetics, the building industry has begun to rely on more often on water repellents as the primary mechanism to maintain and preserve the clean look of new buildings. As a result of this demand, many products are currently commercially available, however, it is important to recognize that the essential functions that these water repellents should address are:
<![if !supportLists]>v <![endif]>Resistance to water intrusion
<![if !supportLists]>v <![endif]>Prevention of water-soluble salts, particularly chloride salts
<![if !supportLists]>v <![endif]>Penetration of repellent treatment to a measurable depth
<![if !supportLists]>v <![endif]>Will not stain surface areas
<![if !supportLists]>v <![endif]>Long-term stability in an alkaline environment
<![if !supportLists]>v <![endif]>Low environmental and health risk
<![if !supportLists]>v <![endif]>UV stability (20+ years)
There are 2 classes of waterproofing products:
1. Film Formers
2. Penetrants / Repellents
Film Formers:
The economics and the ease of application have led to widespread use of film forming water repellents. Products like acrylic paint and silicon polymers are commonly used in the world for waterproofing applications.  These film formers have a particle size greater than 100 nm, which will not allow them to penetrate inside the pores of the building materials but instead form a film covering and protecting the surface from water absorption.  Generally, these polymer films are hydrophobic but they need to be continuous and defect-free and also must be UV resistant.  It is found that during application, ensuring a continuous film on rough surfaces is difficult to achieve which leads to weak points in the film.  Most typical polymer films tend to break down under UV exposure leading to cracking of the films in 2 to 5 year. This leads to failure in terms of losing the hydrophobic water resistant features of the film.
Penetrants / Repellents:
Most penetrants are solvent based, soluble monomeric materials less than 6 m in size which can easily penetrate inside the pores and sub-branches of the pores.  There are two types of penetrants: (i) non reactive and (ii) reactive. 
Non-reactive penetrants are oils and other low viscosity hydrophobic materials, which coat the pores of the substrates and provide water repellency.  However, these types of materials are also biodegradable and lose their hydrophobic characteristics within a year.  Additionally, these products also provide food for mold or fungus growth on the substrate surfaces and into the pores.
Reactive penetrants chemically react with the substrate and provide molecular level hydrophobic protection 3 to 5 mm deep into the substrate.  Therefore, these types of water repellent products provide protection for a long period.  Additionally, the product is bound chemically on a molecular level to the substrate. As a result weathering (UV exposure) and natural abrasion have little impact on the ultimate waterproofing characteristics.
Silanes and Silane / Siloxanes are recognized as a new class of water repellent technology that uses two methods to suppress water intrusion.
Solvent based silane water repellent compounds have been proven to provide long lasting performance and are used widely in USA and Europe.  The two alkyl silanes most often used for waterproofing are: (i) isobutyltrialkoxysilane (ii) n-octyltrialkoxysilane.
The silanes used with water repellent technologies are monomeric materials are known as alkylalkoxysilane. Alkylalkoxysilane has two types of groups (a) alkyl group, R’ and (b) alkoxy groups, (OR) which are reactive with most cementitious building materials.
Alkyl Group
O           R
R’          Si      O      R   
   Alkoxy Groups
O           R

Organosilicon Waterproofing Products:

Alkylalkoxysilane
Most cementitious building materials contain hydroxyl (OH) groups.  These OH groups can chemically react with alkoxy groups of Silane to form permanent siloxane bonds with the substrate.  The alkyl group R’ provides hydrophobicity (water repellency) on the surface. Therefore, these types of products impart water repellency by modifying surface characteristics from hydrophilic to hydrophobic.
Although solvent based silanes can provide superior performance, usage is often limited because of its high cost, flammability and toxicity related to the solvent content limiting its usage to more critical structures. Recently, Zydex Industries in India developed a water repellent technology known as Zycosil, which provides the four most desired properties (Eco Friendly, Easy to apply, Long lasting, Affordable) based on nano technology. Zycosil provides molecular level hydrophobicity to inorganic substrate and is eco-friendly because it is applied in water solution and the VOC per applied square meter is less than 20% of solvent based silanes. The product is based on organosilane chemistry; hence it reacts with the inorganic substrate surface and provides service life of 20 to 30 years service.
Eco-Friendly Water Based Nano Technology – Zycosil: Zycosil is an organosilane product, which forms a particle size of 4-6 m in water and penetrates deep into the building material pores (3-5 mm depth).  The product becomes part of the building material and makes it highly water repellent.
The product has shown 4 major attributes:

<![if !supportLists]>v <![endif]>ZYCOSIL has a long expected life of 20 to 30 years, confirmed by weathering test data conducted with ASTM test methods.
<![if !supportLists]>v <![endif]>ZYCOSIL is diluted 1:10 or more with tap water, and emits an extremely small amount of organic solvent into the atmosphere, making it eco-friendly and non flammable.
<![if !supportLists]>v <![endif]>ZYCOSIL can be applied by brush, spray or roller techniques, making it user friendly. ZYCOSIL provides water repellency at a material cost lower than existing technology and products, which can give a similar initial performance.
Zycosil Treated Substrate Testing:

Rilem Test:
The Rilem tube was affixed on the substrate surface.  Water was filled up to the 5ml mark.  The drop in water level was observed over a 20-minute period.  The hydraulic pressure generated on the surface was equivalent to 140 Km/hr wind driven rain.
Untreated:                                
The water level did not drop for a 24 hour period on the Zycosil treated cement block. The water level of untreated cement blocks dropped to about the 2.5 ml mark after 20 minutes.  The Rilem test is also used for water absorption rate.  The absorption rate is determined and compared with the untreated samples.
Treated:
Zycosil treated samples (brick, concrete, cement sheet, plaster, stone, etc.) reduced water absorption rates by over 99 %.
Accelerated weathering:
Weathering Cycle: The UV exposure was set according to ASTM G-154 (21 hours), followed by rain showers (1 hour) and drying at 110C (2 hours).
The Zycosil treated samples (Concrete blocks, Bricks, Plaster, Sand stone, and Cement Sheet) have undergone over 80 cycles.
All the Samples retained over 98 % of water repellency, after 80 cycles.
Water uptake test:
This test was carried out according to ASTM 6489 method. The Zycosil treated samples were weighed to the nearest 0.01 grams, and then placed with treated or exposed surface only, in a tank containing several inches of tap water for a period of 24 hours.  The samples were then removed from the water, towel dried and reweighed.  The initial and final weights were used to calculate the 24-Hour Treated Water uptake values.  These values were compared with the untreated samples.
Zycosil treated samples showed over 90 % reduction in water uptake of water.


CASE STUDY :
A) Method Statement for roof waterproofing works:
1.Scope Of Work:
      This method statement covers the roof water proofing system intended to be used for the above mentioned case study project.
2.Approved Applicator:
M/s Water Seal Co.LLC.Abudhabi
3.Materials Used :
<![if !supportLists]>v <![endif]>Masterseal 420:Bitumen Emulsion primer from M/S BASF
<![if !supportLists]>v <![endif]>DAREX AE4: Foaming agent for foam concrete from M/S Grace
<![if !supportLists]>v <![endif]>IMI Primer: Bituminous primer from M/S IMI
<![if !supportLists]>v <![endif]>4mm thick EKOGUARD: APP Modified bitumen membrane from M/S IMI
<![if !supportLists]>v <![endif]>ESSCOFOAM 35-6,50mm thick insulation board from M/S ESSCOFOAM
<![if !supportLists]>v <![endif]>A281 Geotextile Fabric: Geo textile separation layer from M/s ALIAF Industries
<![if !supportLists]>v <![endif]>Roof tiles: 500x500x50 mm thick cement tiles from M/S Terrazzo
SURFACE PREPARATION:
The surface shall be properly prepared by brushing, clearing and leaving the surface free from dust, dirt, grease, loose or projecting particles of mortar etc. The installation of all the pipes, cables and fixing of rain water outlets shall be done prior to waterproofing. All the corners and penetrations shall have cement sand angle fillets.

APPLICATION OF COLD APPLIED COATING:
<![if !supportLists]>v <![endif]>After surface is thoroughly cleaned, first coat of approved masterseal 420, and shall be applied at a rate of one litre/sq.m.
<![if !supportLists]>v <![endif]>Next day, 2nd coat shall be applied at a rate of one litre/sq.m.But in the opposite direction i.e 2nd coat is applied at right angle to first coat.
<![if !supportLists]>v <![endif]>The coating shall be allowed to dry for minimum of 2 days.
FOAM CONCRETING:
After the application of masterseal 420 and drying, minimum 50mm thick foam concrete shall be laid as per the mix design already submitted. The initial setting time of foam concrete under present weather is 18 to 24 hrs. Curing for 3 days is required.
APPLICATION OF PRIMER:
After curing of foam concrete is completed, all the areas where the membrane has to be laid shall receive 2 coats of approved IMI primer applied by brush or roller at the rate of 250gm/sq.m.
Primer shall be allowed to dry fully before membrane application.
Drying of primer : 12-24 hrs, depending up on weather conditions
APPLICATION OF WATERPROOFING MEMBRANE:
Approved waterproofing membrane i.e EKOGURAD 200 membrane is delivered in 1x10m roll. One layer of 4mm thick approved waterproof membrane shall be torch applied over the primer surface.
Membrane overlaps shall be 100mm for side and 150mm for ends. Tolerance is 10%. Whatever is the quality of the first overlap torching, the seaming of the edges of the membrane shall be done in 2nd operation to allow for checking and re-torching of potential gaps. All membranes overlaps shall be fully torched. Membrane corners and angles shall be fully torched. Any void or air gaps must be corrected if found.
For Skirting, a 4mm thick APP elastomeric bitumen membrane (1 layer) with self protection granule finish, 30 cm wide shall be terminated in to waterproofing termination groove and sealed with bituminous sealant.
Water leak test:
After the membrane is laid, all roof openings shall be temporarily plugged to prevent leak from the opening during the water leak test. It shall be then offered for inspection by submitting an inspection request. Leak test shall be carried out for 48 hrs by filling the roof with water for a height of 50 mm. At the completion of successful water leak test, drain plugs shall be removed and subsequent activity can be started.
Installation of insulation boards :
Upon successful completion of water leak test, 50mm thick approved thermal insulation boards i.e ESCOFOAM shall be placed over the membrane. The fixing of the insulation boards is done by fixing the male butt joints in to the female. It has to be made sure that all the joints are properly aligned and in place.
Installation of Geotextile Separation layer:
After the insulation boards are laid, one layer of approved geotextile fabric i.e A281 shall be laid on top of the polystyrene boards. The overlap shall be 50mm.
Installation of Aluminium Flashing & Mastic Sealant:
The aluminium flashing of 1.5 mm thickness and approximately 150 – 200mm width shall be fixed mechanically by stainless steel screws. The distance between the screws shall not be more than 70 cm. The overlap shall be 2cm. After the fixing of aluminium flashing, polysulphide sealant i.e POLYSEAL PS from M/S Polybit Industries shall be applied inside the top bend of aluminium flashing.
   


B) Method Statement for Basement waterproofing works:
Scope Of Work:
      This method statement covers the roof water proofing system intended to be used for the above mentioned case study project.
2.Approved Applicator:
M/s Water Seal Co.LLC.Abudhabi
3.Materials Used :
<![if !supportLists]>v <![endif]>Masterseal 420:Bitumen Emulsion primer from M/S BASF
<![if !supportLists]>v <![endif]>DAREX AE4: Foaming agent for foam concrete from M/S Grace
<![if !supportLists]>v <![endif]>4mm thick EKOGUARD: APP Modified bitumen membrane from M/S IMI
<![if !supportLists]>v <![endif]>ESSCOFOAM 35-6,50mm thick insulation board from M/S ESSCOFOAM
<![if !supportLists]>v <![endif]>BITUBOARD: Bituminous membrane from M/S Bitustick industries.
SURFACE PREPARATION:
The surface shall be properly prepared by brushing, clearing and leaving the surface free from dust, dirt, grease, loose or projecting particles of mortar etc. The installation of all the pipes, cables and fixing of rain water outlets shall be done prior to waterproofing. All the corners and penetrations shall have cement sand angle fillets.
APPLICATION OF COLD APPLIED COATING:
<![if !supportLists]>v <![endif]>After surface is thoroughly cleaned, first coat of approved masterseal 420, and shall be applied at a rate of one litre/sq.m.
<![if !supportLists]>v <![endif]>Next day, 2nd coat shall be applied at a rate of one litre/sq.m.But in the opposite direction i.e 2nd coat is applied at right angle to first coat.
<![if !supportLists]>v <![endif]>The coating shall be allowed to dry for minimum of 2 days.
FOAM CONCRETING/SCREED CONCRETING:
After the application of masterseal 420 and drying, minimum 50mm thick foam concrete shall be laid as per the mix design already submitted. The initial setting time of foam concrete under present weather is 18 to 24 hrs. Curing for 3 days is required.
APPLICATION OF PRIMER:
After curing of foam concrete is completed, all the areas where the membrane has to be laid shall receive 2 coats of approved IMI primer applied by brush or roller at the rate of 250gm/sq.m. Primer shall be allowed to dry fully before membrane application.
Drying of primer : 12-24 hrs, depending up on weather conditions
APPLICATION OF WATERPROOFING MEMBRANE:
Approved waterproofing membrane i.e EKOGURAD 200 membrane is delivered in 1x10m roll. One layer of 4mm thick approved waterproof membrane shall be torch applied over the primer surface.
Membrane overlaps shall be 100mm for side and 150mm for ends. Tolerance is 10% . whatever is the quality of the first overlap torching, the seaming of the edges of the membrane shall be done in 2nd operation to allow for checking and re-torching of potential gaps. All membranes overlaps shall be fully torched. Membrane corners and angles shall be fully torched. Any void or air gaps must be corrected if found.
For Skirting, a 4mm thick APP elastomeric bitumen membrane (1 layer) with self protection granule finish, 30 cm wide shall be terminated in to waterproofing termination groove and sealed with bituminous sealant.


Stability Analysis of Buildings and Restoration

Today’s modernization and rapid industrialization has resulted in construction of several wonderful structures, with reinforced cement conc...